Okeyinka Emmanuel -
Resume OKEYINKA EMMANUEL Scheduler/planner E-Mail:
emmanuelokeyinka@gmail.com
Phone: +1 (832) - 282-2139
SUMMARY Experienced Project Scheduler with over five
years experience in Project Planning, Monitoring and Control. Knowledge areas
include: Critical Path Methodology (CPM), Progress Measurement and Earned
Value Management (EVM) techniques (PV, EV, AC, SPI, and CPI). Deeply
grounded in Subsea Projects & Equipments and able to manage project
schedules from start to finish, reporting, forecasting, updating and
troubleshooting by identifying and developing mitigation approach. Exposed to
different project phases like: Pre-Front End Engineering Design (Pre-FEED),
FEED, and Detailed Engineering, Procurement and Construction (EPC). Expert in
utilizing Primavera P6 and Microsoft Office Suites PROFESSIONAL EXPERIENCES AVEON OFFSHORE LTD
LAGOS State,
Nigeria
Project Planner/Scheduler
November 2012 – JULY 2014 • Created bi-weekly and
monthly reports based on analysis of the overall project schedule and tracked
it against the baseline, specifying areas of variance and recommending
remedial action to the Project Manager. • Prepared and issued progress
reports such as S-Curves and Histograms. • Developed and maintained a
Work Breakdown Structure and overall plan for the project using Primavera P6,
identified the critical path and areas of concern for the overall project. • Maintained and updated the
schedule on regular interval and as required. Prepared Look-Ahead schedules
for discipline leads. Ensure all work and job plans meet regulatory and HSSE
requirements. • Reviewed schedules submitted
by leads, and other third parties and advise of potential schedule/or cost
impacts on the project. Established logic driven milestones for the total
project. • Prepared man-hour
forecasting, reviewed schedules with Project Manager and leads, and attended
project team meetings, both internal and at clients office. • Created detailed schedules
and performed analysis to ensure adherence to budgetary guidelines. Conducted
project planning and post implementation review to ensure project was on
track, on time and within schedule. • Managed site project control
functions and tracked productivity of engineers. Also tracked procurement
packages and reports. Created reports and curves for analyzing equipment
deliveries which shows required on site dates (ROS), actual on site and
forecast equipment delivery on site dates. • Created a Level 3 Schedule
to ensure achievements of projects goals. • Additional responsibility
included interface with management to develop a Level 1 Company Plan schedule
and cost basis for upper management. MIGHTY DRILLS LTD
Oyo State, Nigeria Scheduler
SEPTEMBER 2011 - NOVEMBER 2012
·
Worked on schedules for drilling equipment, shipment
and delivery ·
Developed work breakdown structures (WBS) and worked
closely with the engineering team to prepare schedules ·
Created and maintained schedules based on the WBS, with
task definitions and relationships ·
Performed document control functions in order to become
familiar with engineering deliverables and tracking progress of engineering
activities ·
Prepared work instructions on new and existing projects
to establish better way of managing them ·
Worked closely with the team to determine activity
sequence and activity duration ·
Monitored actual progress, compared to baseline and
reported progress to forecast project-end estimates ·
Researched and reported delayed activities and proposed
remedial actions to accelerate progress ·
Developed and analyzed project schedule to align with
project scope and deadline ·
Integrated different project together for master
schedule while using activity code to analyze reports ·
Monitored project expenses against budget, monitored
weekly on-site activities and prioritized procurement of materials MIGHTY DRILLS LTD
Oyo State, Nigeria
PROCUREMENT SPECIALIST
DECEMBER 2009 – SEPTEMBER 2011 ·
Coordinated with various departments for purchasing
activities and maintaining inventory in an effective manner ·
Administered all purchase requisitions and processed
all purchase change orders ·
Performed cost analysis on all major commodities and
planned its volume ·
Monitored work of assigned subcontractors and scheduled
its cost ·
Developed new supply sources and recommended various
cost saving proposals ·
Collaborated with Quality Control and suppliers and
resolved all quality issues ·
Coordinated with daily and third party logistics
provider and managed inventory ·
Monitored all sending materials orders and ensured
appropriate data transmissions according to schedule ·
Evaluated daily inventory receipts and prepared reports
to be presented to third party logistics provider ·
Provided support to procurement management teams and
answered all inquiries for product availability ·
Ensured compliance to all company and departmental
guidelines ·
Interacted with all departments in the drilling division,
Regional Managers, and the main office in Other City. ·
Changed department from procurement to planning EDUCATION B.ENG. METALLURGY &
MATERIALS ENGINEERING
SPECIFIC TECHNICAL EXPERTISE v Primavera P6 and Microsoft Project v Microsoft Office Suites (Excel, Work, PowerPoint and Outlook) v